Low-code and no code software development solutions have emerged as viable and convenient alternatives to the traditional development process.
Low-code is a rapid application development (RAD) approach that enables automated code generation through(71) building blocks like drag-and-drop and pull-down menu interfaces.This (72) allows low-code users to focus on the diferentiator rather than the common denominator of programming. Low-code is a balanced middle ground between manual coding and no-code as its users can still add code over auto-generated code.While in low-code there is some hand holding done by developers in the form of scripting or manual coding, no-code has a completely (73) approach, with 100% dependence on visual tools.
A low-code application platform (LCAP)——also called a low-code development platform (LCDP)——contains an integrated development environment (IDE) with (74) features like APIs, code templates, reusable plug-in modules and graphical connectors to automate a significant percentage of the application development process.LCAPs are typically available as cloud-based Platform-as-a-Service (PaaS) solutions.
A low-code platform works on the principle or lowering complexity by using visual to and techniques like? process modeling. where users employ visual tools to define workflobusiness rules, user interfaces and the like.Behind the scenes, the complete workflovautomatically converted into code. LCAPs are used predominantly by professional developeautomate the generic aspects of coding to redirect effort on the last mile of (75).
问题1:
A.visual
B.component-based
C.object-oriented
D.structural(72)
问题2:
A.block
B.automation
C.function
D.method(73)
问题3:
A.modern
B.hands-off
C.generic
D.labor-free(74)
问题4:
A.reusable
B.built-in
C.existed
D.well-known(75)
问题5:
A.delivery
B.automation
C.development
D.success
正确答案及解析
正确答案
解析
包含此试题的试卷
你可能感兴趣的试题
在几种不同类型的软件维护中,通常情况下()所占工作量最大。
-
- A.更正性维护
- B.适应性维护
- C.完善性维护
- D.预防性维护
- 查看答案
在()中,项目经理的权力是最小的。
-
- A.强矩阵型组织
- B.平衡矩阵组织
- C.弱矩阵型组织
- D.项目型组织
- 查看答案
在项目实施的过程中,项目经理通过项目周报中的项目进度分析图表发现机房施工进度有延期风险。项目经理立即组织相关人员进行分析,下达了关于改进措施的书面指令。该指令属于( )
-
- A.检查措施
- B.缺陷补救措施
- C.预防措施
- D.纠正措施
- 查看答案
-