以下是某工程进度网络图,如果因为天气原因,活动③→⑦的工期延后2天,那么总工期将延后 ( ) 天。

高级信息系统项目管理师,章节练习,基础复习,项目进度管理

  • A.0
  • B.1
  • C.2
  • D.3

正确答案及解析

正确答案
A
解析

首先要识别本工程的关键路径为:ACDHJ、ACEHJ。活动3—7即活动G的总时差为2,故活动G不在关键路径上,且由于活动I的自由时差FF活动17-15=2,活动G的自由时差TF活动G=12-12=0,但活动G的总时差TF活动G=2,故活动G的工期延后2天,活动I历时不变,总工期将不受影响。

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案

相关题库更多 +