某项目2016年投资额12万元,2018年开始取得项目的净收益(产品一原料辅料及公用工程)6万元/年,2018-2021年每年还会产生其他成本(包括人员工资、管理成本、制造成本等)1.1万元/年;増值税0.35万元/年、营业税金及附加0.05万元/年。则该项目的静态投资回收期为(66)年,截止到2021年底该项目的投资收益率是(67)。
- A.2.0
- B.2.67
- C.3.25
- D.3.67
正确答案及解析
正确答案
解析
本题考查的是静态投资回收期及投资收益率。
静态投资回收期=(累计净现金流量开始出现正值的年份数-1)+上一年累计净现金流量的绝对值/出现正值年份的净现金流量。

包含此试题的试卷
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案