题目详情

下图是某项目的进度网络图,则在保障不会影响项目总工期的情况下,活动E最多能拖延( )天。

高级信息系统项目管理师,历年真题,2021年下半年《信息系统项目管理师》真题

  • A.0
  • B.1
  • C.2
  • D.3

正确答案及解析

正确答案
A
解析

本题考查的是关键路径法。

根据图可以分析出E在关键路径上,关键路径上的总浮动时间和自由浮动时间都为0。

包含此试题的试卷

你可能感兴趣的试题

单选题

( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.

  • A.Plan Quality Management
  • B.Manage Quality
  • C.Control Quality
  • D.Project Charter
查看答案
单选题

( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.

  • A.Plan Scope Management
  • B.Collection Requirements
  • C.Validate Scope
  • D.Control Scope
查看答案
单选题

The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).

  • A.technology management process
  • B.resource management process
  • C.quality management process
  • D.risk management process
查看答案
单选题

( )is a decentralized database,ensure that the data will not be tampered with and forged.

  • A.Artificial intelligence
  • B.Blockchain
  • C.Sensing technology
  • D.Big datA
查看答案
单选题

( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.

  • A.Cloud computing
  • B.Big datA
  • C.Blockchain
  • D.Internet of things
查看答案

相关题库更多 +