下图表示某项目各个活动关系及乐观、最可能、悲观完成时间,假设各活动的三种完成时间服从β分布,按照三点估算法该项目标准差为3.2天,则项目在( )完成的概率为95%。

- A.42.6天到55.4天
- B.45.8天到52.2天
- C.61.4天到74.6天
- D.64.7天到71.3天
正确答案及解析
正确答案
解析
本题考查的是计划评审技术。
根据三点估算法计算出各活动的工期,例如A活动工期=(8+16+4×12)/6=12天,依此类推B活动工期19天,C活动工期7天,D活动工期天13天,E活动工期6天,F活动工期12天。然后再根据紧前紧后关系画出单代号网络图,找出关键路径ABEF总工期为49天。完成95%的概率是正负两倍标准差,即42.6天到55.4天。
包含此试题的试卷
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案