( )的准确性取决于模型的成熟度和基础数据的可靠性。
- A.类比估算
- B.三点估算
- C.自下而上
- D.参数估算
正确答案及解析
正确答案
解析
类比估算:是一种使用相似活动或项目的历史数据,来估算项目当前活动或项目的持续时间或成本的技术。
三点估算:通过考虑估算中的不确定性和风险,可以提高活动持续时间估算的准确性。
自下而上估算:先估算单个活动成本、再汇总或“滚动”到更高层次。
参数估算:基于历史数据和项目参数、准确性取决于参数模型的成熟度和基础数据的可靠性。
包含此试题的试卷
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案