某软件项目的活动图如下图所示,其中顶点表示项目里程碑,连接顶点的边表示包含的活动,边上的数字表示该活动所需的天数,则完成该项目的最少时间为(  )天。活动BD最多可以晚(  )天开始而不会影响整个项目的进度。
问题1选项
A.9
B.15
C.22
D.24
问题2选项
A.2
B.3
C.5
D.9
正确答案及解析
正确答案
DA
            解析
暂无解析
        包含此试题的试卷
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
- 
                
- A.Plan Quality Management
 - B.Manage Quality
 - C.Control Quality
 - D.Project Charter
 
 - 查看答案
 
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
- 
                
- A.Plan Scope Management
 - B.Collection Requirements
 - C.Validate Scope
 - D.Control Scope
 
 - 查看答案
 
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
- 
                
- A.technology management process
 - B.resource management process
 - C.quality management process
 - D.risk management process
 
 - 查看答案
 
( )is a decentralized database,ensure that the data will not be tampered with and forged.
- 
                
- A.Artificial intelligence
 - B.Blockchain
 - C.Sensing technology
 - D.Big datA
 
 - 查看答案
 
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
- 
                
- A.Cloud computing
 - B.Big datA
 - C.Blockchain
 - D.Internet of things
 
 - 查看答案