某网络工程计划图26-2如下所示,边上的标记为任务编码及其需要的完成时间(天),则整个工程的工期为( )。
- A.21
- B.22
- C.25
- D.29
正确答案及解析
正确答案
解析
关键路径法(CriticalPathMethod,CPM),在一个项目中,只有项目网络中最长的或耗时最多的活动完成之后,项目才能结束,这条最长的活动路线就叫关键路径,组成关键路径的活动称为关键活动。整个项目工期是由最长的线路来决定的。寻找最长路径1→2→3→4→5→6,路径之和就是整个工程的工期。
包含此试题的试卷
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案