进度安排的常用图形描述方法有Gantt图和PERT图。Gantt图不能清晰地描述(  );
PERT图可以给出哪些任务完成后才能开始另一些任务。下图所示的PERT图中,事件6的最晚开始时刻是(  )。
中级软件设计师,历年真题,2010年上半年(上午)《软件设计师》真题
问题1选项
A.每个任务从何时开始
B.每个任务到何时结束
C.每个任务的进展情况
D.各任务之间的依赖关系
问题2选项
A.0
B.3
C.10
D.11

正确答案及解析

正确答案
DC
解析
暂无解析

包含此试题的试卷

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案

相关题库更多 +