因公司进行一个项目其包含A,B,C,D,E,F,G七个活动,各活动的历史估算和活动间的逻辑关系如下表所示,该项目的工期是( )天。因该项目对资源限制和项目的不确定性,为保证项目的按质按量的完成,项目经理薛大龙采用了在原进度计划采用了关键链路法,设置了项目的接驳缓冲为1天和项目缓冲为4天,项目总工期是(请作答此空)。

- A.19
- B.20
- C.23
- D.24
正确答案及解析
正确答案
解析
关键路径是ADFG,工期是19天。因采用了关键链路法,在原有的工期上进行了接驳缓冲和项目缓冲,关键路径是ADFG,总工期是=19+4=23天
包含此试题的试卷
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案