( )is a project management technique for measuring projectPerformance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.
- A.Critica1 path method(CPM)
- B.Earned value management(CEV)
- C.Net present value method(NPVM)
- D.Expert judgment method(EJM)
正确答案及解析
正确答案
B
解析
暂无解析