某工程有七个作业A~G,按计划,完成各作业所需的时间以及作业之间的衔接关系见下表:
按照上述计划,该工程的总工期预计为( )周。
在工程实施了10周后,经理对进度进行了检查,结果是:作业A和B已经完成,作业D完成了30%,作业E完成了25%,其他作业都还没有开始。
如果随后完全按原计划实施,则总工期将( )完成。
问题1选项
A.20
B.25
C.33
D.41
问题2选项
A.提前1周
B.推迟1周
C.推迟2周
D.推迟3周
正确答案及解析
正确答案
解析
包含此试题的试卷
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案