某项目包含A、B、C三项主要活动,项目经理在成本估算时采用自下而上的方法,分别估算出三项活动的成本分别为13万元、23万元和8万元,同时为了应对未来可能遇到的不确定因素,预留了10万元的管理储备,同时为每个活动预留了2万元的准备金。该项目的总预算为( )万元。项目进行到第二个月时,实际花费为20万元,完成总工作量的30%。如果项目按照当前绩效继续进展下去,预测项目的完工尚需成本ETC约为( )万元。
问题1选项
A.44
B.54
C.60
D.50
问题2选项
A.46.7
B.40.7
C.45
D.46
正确答案及解析
正确答案
解析
包含此试题的试卷
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案