The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ).
- A.Cost Variance
- B.Schedule Variance
- C.Earne
- D.Index
正确答案及解析
正确答案
A
解析
BCWP与ACWP之间的差值是 。
A.成本偏差 B.进度偏差 C.挣值 D. 成本绩效
The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ).
BCWP与ACWP之间的差值是 。
A.成本偏差 B.进度偏差 C.挣值 D. 成本绩效