Estimating activity
durations uses information on activity scope of ( ) , required resource types, estimated
resource quantities, and resource calendars.
- A.milestone
- B.baseline
- C.quality
- D.work
正确答案及解析
正确答案
D
解析
暂无解析
Estimating activity
durations uses information on activity scope of ( ) , required resource types, estimated
resource quantities, and resource calendars.