你受雇于一个政府机构来管理一具为期3年、预算达300万美元的项目。如果项目有变更需求,人就需要在每个财政年度的年底有更多的资金注入。你可以在你的项目中使用这些资金。你决定要建立一个成本变更控制系统,这样做的目的是( )
- A.明确什么时候向项目添加应急资金
- B.明确定义变更成本基线的程序
- C.判断成本变动发生的原因
- D.判断是否需要修改预算
正确答案及解析
正确答案
解析
成本变更控制系统包括文件、跟踪和年批准变更需要的批准级别。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案