项目进度表至少包括每项计划活动的计划开始日期与计划完成日期,常见的做法是用一种或多种格式的图形表示。在下面的图表中,常用于表示项目进度表的是( )
- A.横道图
- B.排列图
- C.鱼骨图
- D.趋势图
正确答案及解析
正确答案
解析
横道图用横道表示活动,注明了活动的开始与结束日期,以及活动的预期持续时间。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案