某大型项目进行到两年时,使用挣值法所需的三个中间变量的数值分别是:计划值PV为400万元,实际成本AC为200万元,挣值EV为100万元。基于该项目的成本偏差,下列描述中正确的是( );基于该项目的成本绩效指数,下列描述中正确的是成本绩效指数小于1,且实际发生的成本是预算成本的2倍。
- A.项目成本偏差为负,且项目处于超支状态
- B.项目成本偏差为正,且项目处于超支状态
- C.项目成本偏差为负,且项目处于成本节约状态
- D.项目成本偏差为正,且项目处于成本节约状态
正确答案及解析
正确答案
解析
CV=AC–PV=200-400=-200<0,因此成本偏差为负,项目处于超支状态。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案