题目详情

某项目包含A、B、C、D、E、F、G七个活动,各活动的历时估算和活动间的逻辑关系如下表所示,活动C的总浮动时间是1天,该项目工期是( )天

高级信息系统项目管理师,章节练习,基础复习,章节冲刺

  • A.13
  • B.14
  • C.15
  • D.16

正确答案及解析

正确答案
C
解析

高级信息系统项目管理师,章节练习,基础复习,章节冲刺

由图可知,关键路径ADFG,工期2+6+4+3=15C的总浮动时间=8-7=1

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案

相关题库更多 +