图4是一个软件项目的活动图,其中顶点表示项目里程碑,边表示包含的活动,边上的权重表示活动的持续时间,则里程碑()在关键路径上。

- A.1
- B.2
- C.3
- D.4
正确答案及解析
正确答案
解析
从开始顶点到结束顶点的最长路径为关健路径(临界路径),关键路径上的活动为关键活动。在本题中找出的最长路径是Start→2→5→7→8→Finish,其长度为8+15+15+7+20=65,而其它任何路径的长度都比这条路径小,因此我们可以知道里程碑2在关键路径上。
你可能感兴趣的试题
Anetwork attack is an attempt to gain(71)access to an organization’s network,with the objective of stealing data or performing other malicious activities.Plagiarism is A(72)-of-service(DoS)attack is a cyber-attack in which the attacker seeks to make a machine or network resource unavailable to its intended users by temporarily or indefinitely disrupting services of a host connected to a network.In the case of a simple attack,a(73)could have a simple rule added to deny all incoming traffic from the attackers,based on protocols,ports,or the originating IP addresses.In a(74)DoS(DDoS)attack wangwangwang,the incoming traffic flooding the victim originates from(75)different sources.This effectively makes it impossible to stop the attack simply by blocking a single source问题1:
A.unauthorized
B.authorized
C.normal
D.frequent
问题2:
A.defense
B.denial
C.detection
D.decision
问题3:
A.firewall
B.router
C.gateway
D.switch
问题4:
Adamaged
B.descriptive
C.distributed
D.demanding
问题5:
A.two
B.many
C.much
D.ten
- 查看答案
以下关于信息化项目成本估算的描述中,不正确的是( )。
-
- A.项目成本估算指设备采购、劳务支出等直接用于项目建设的经费估算
- B.项目成本估算需考虑项目工期要求的影响,工期要求越短成本越高
- C.项目成本估算需考虑项目质量要求的影响,质量要求越高成本越高
- D.项目成本估算过粗或过细都会影响项目成本
- 查看答案
《中华人民共和国数据安全法》由中华人民共和国第十三届全国人民代表大会常务委员会第二十九次会议审议通过,自( )年 9 月 1 日起施行。
-
- A.2019
- B.2020
- C.2021
- D.2022
- 查看答案
某存储系统规划配置 25 块 8TB 磁盘,创建 2 个 RAID6 组,配置 1 块热备盘,则该存储系统实际存储容量是( )。
-
- A.200T
- B.192TB
- C.176TB
- D.160TB
- 查看答案
以下关于层次化网络设计模型的描述中,不正确的是( )。
-
- A.终端用户网关通常部署在核心层,实现不同区域间的数据高速转发
- B.流量负载和 VLAN 间路由在汇聚层实现
- C.MAC 地址过滤、路由发现在接入层实现
- D.接入层连接无线 AP 等终端设备
- 查看答案