小李所负责的项目已经完成了20%。最近一次的挣值分析结果显示,成本绩效指数(CPI)为0.67,进度绩效指数(SPI)为0.87。在这种情况下,小李应该 ( ) 。
- A.实施额外的资源计划编制,增加资源,并且在需要的时候进行超时工作,以完成已预算好的工作量
- B.为进度重新设定基准,然后使用蒙特卡罗分析
- C.实施风险应对审计以帮助控制风险
- D.更新风险的识别、定性风险分析和定量风险分析
正确答案及解析
正确答案
解析
当前CPI及SPI均小于1,说明项目当前成本超支、进度落后。应实施风险应对。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案