( )不属于风险识别阶段的成果。
- A.低优先级风险的监视表
- B.己识别出的风险列表
- C.风险征兆或警告信号
- D.潜在的风险应对方法列表
正确答案及解析
正确答案
解析
风险识别阶段的输出包括:(1)已识别的风险列表;(2)风险的征兆或聱告信号;(3)潜在风险应对方法列表;(4)风险根本原因;(5)更新的风险分类低优先级风险监视表;低优先级风险的监视表(在风险定性分析过程中不重要的风险将被放在监视列中以备继续监视)是定性风险分析阶段的输出产物。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案