项目经理在某项目实施阶段的中期发现,由于未预料到的变更,项目经费要花光了,此时应 ( )

  • A.对项目进行赶工或快速跟进
  • B.重新评估风险分析结果和应急资金
  • C.要求对项目预算做变更
  • D.使用不对项目收费的资源

正确答案及解析

正确答案
B
解析

选项A和C并不能解决潜在的问题,选项D缺乏职业道德。重新评估风险分析结果和应急资金,既考虑了现在遇到的问题,又对未来重新进行了调研,所以正确答案为选项B。

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案

相关题库更多 +