某系统集成企业为做好项目风险管理,给风险定义了3个参数。①风险严重性:指风险对项目造成的危害程度;②风险可能性:指风险发生的几率;③风险系数:是风险严重性和风险可能性的乘积。其中,对项目进度延误、工作量偏差的风险严重性等级和风险可行性等级如下表所示:假定该企业将风险系数大于等于10的情况定义为红灯状态,需要优先处理,则下列 ( ) 的情况属于红灯状态。

- A.进度延误15%,工作量偏差15%,发生几率为0.5
- B.进度延误15%,工作量偏差35%,发生几率为0.2
- C.进度延误25%,工作量偏差15%,发生几率为0.4
- D.进度延误15%,工作量偏差25%,发生几率为0.4
正确答案及解析
正确答案
解析
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案