题目详情

一项任务的最早开始时间是第3天,最晚开始时间是第13天,最早完成时间是第9天,最晚完成时间是第19天。该任务____ 。

  • A.在关键路径上
  • B.有滞后
  • C.进展情况良好
  • D.不在关键路径上

正确答案及解析

正确答案
D
解析

因该任务有10天的浮动时间,可以断定它不在“关键路径上”。关键路径上的任务浮动时间皆为0。题干中没有交代该项目是处于哪个阶段,也没有交代该任务的基准进度和预算,因此不能断定它“有滞后”,还是“进展情况良好”。

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案

相关题库更多 +