以下工程进度网络图中,若结点0和6分别表示起点和终点,则关键路径为 ( ) 。

- A.0→1→3→6
- B.0→1→4→6
- C.0→1→2→4→6
- D.0→2→5→6
正确答案及解析
正确答案
解析
本题考查应试人员关键线路方面的知识。关键线路有两种定义:①在一条线路中,每个工作的时间之和等于工程工期,这条线路就是关键线路。②若在一条线路中,每个工作的时差都是零,这条线路就是关键线路。根据定义我们可以求出关键线路是0→1→2→4→6,正确答案是C。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案