题目详情

某项目成本偏差(CV)大于0,进度偏差(SV)小于0,则该项目的状态是 ( ) 。

  • A.成本节省、进度超前
  • B.成本节省、进度落后
  • C.成本超支、进度超前
  • D.成本超支、进度落后

正确答案及解析

正确答案
B
解析

挣值分析是测量绩效最常用的方法。挣值涉及计算每个活动的4个关键值:计划值(PV)、实际成本(AC)、挣值(EV)、剩余工作的成本估算(ETC)。CV=EV-AC>0,表明项目实施处于成本节省状态;SV(SV=EV-PV<0,表明项目实施落后于计划进度。因此该项目的状态是“成本节省、进度落后”。

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案

相关题库更多 +