某项目成本偏差(CV)大于0,进度偏差(SV)小于0,则该项目的状态是 ( ) 。
- A.成本节省、进度超前
- B.成本节省、进度落后
- C.成本超支、进度超前
- D.成本超支、进度落后
正确答案及解析
正确答案
解析
挣值分析是测量绩效最常用的方法。挣值涉及计算每个活动的4个关键值:计划值(PV)、实际成本(AC)、挣值(EV)、剩余工作的成本估算(ETC)。CV=EV-AC>0,表明项目实施处于成本节省状态;SV(SV=EV-PV<0,表明项目实施落后于计划进度。因此该项目的状态是“成本节省、进度落后”。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案