分析成本构成结果,找出各种可以相互替代的成本,协调各种成本之间的关系,属于( ) 的内容。
- A.识别和分析项目成本构成科目
- B.成本估算
- C.成本预算
- D.成本审计
正确答案及解析
正确答案
解析
编制项目成本估算需要进行三个主要步骤。首先,识别并分析项目成本的构成科目,即项目成本中所包括的资源或服务的类目,例如:人工费、材料费、咨询费等。其次,根据已识别的项目成本构成科目,估算每一成本科目的成本大小。最后,分析成本估算结果,找出各种可以相互替代的成本,协调各种成本之间的比例关系。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案