某一项目,初始投资为2000万元,该项目从投产年开始每年的净收益如下表所示,则该项目的静态投资回收期约为( )年。

高级信息系统项目管理师,章节练习,基础复习,项目成本管理

  • A.2.9
  • B.3.9
  • C.2.7
  • D.3.8

正确答案及解析

正确答案
B
解析

静态投资回收期=累计净现金流量第一次出现正值的年份-1+该年初尚未回收的投资的绝对值÷该年净现金流量=4-1+700/800=3.91没有特别说明,建设期是包括在投资回收期的。

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案

相关题库更多 +