某项目计划分为立项、实施和运维三个阶段。财务部给该项目的预算金额不超过80万元。项目经理估算立项阶段的成本为20万元,实施阶段的成本为50万元,运维阶段的成本为30万元。若用自底向上法对该项目的成本进行估算,则估算值应为 ( ) 万元。
- A.70
- B.80
- C.90
- D.100
正确答案及解析
正确答案
解析
自底向上法,就是先估算单个工作包的成本,然后将这些详细成本汇总得到更高层的成本。所以将立项、实施和运维三个阶段成本相加就得到项目估算值,该值为100。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案