按照索赔程序,索赔方要在索赔通知书发出后 ( ) 内,向监理方提出延长工期和(或)补偿经济损失的索赔报告及有关资料。

  • A.2 周
  • B.28 天
  • C.30 天
  • D.3 周

正确答案及解析

正确答案
B
解析

按照索赔程序,当出现索赔事项时,首先由索赔方以书面的索赔通知书形式,在索赔事项发生后的 28 天以内,向监理工程师正式提出索赔意向通知书。在索赔通知书发出后的 28 天内,向监理工程师提出延长工期和(或)补偿经济损失的索赔报告及有关资料。因此选择 B。

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案

相关题库更多 +