某大型项目的变更策略规定:把变更分为重大、紧急、一般和标准变更,并规定了不同级别的审批权限,比如重大变更由CCB审批,并规定标准变更属于预授权变更,可不用再走审批流程。此项目变更策略 ( ) 。
- A.可行
- B.不可行,主要是变更不能分级别,应统一管理
- C.不可行,分四级可以,但审批都应由CCB批准
- D.不可行,标准变更规定有问题
正确答案及解析
正确答案
解析
用排除法。变更都必须审批。但不一定全部由CCB批准。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案