某项目已制定了详细的范围说明书,并完成了WBS 分解。在项目执行过程中,项目经理在进行下一周工作安排的时候,发现 WBS 中遗漏了一项重要的工作,那么接下来他应该首先 ( ) 。
- A.组织项目组讨论,修改WBS
- B.修改项目管理计划,并重新评审
- C.汇报给客户,与其沟通,重新编写项目文档
- D.填写项目变更申请,对产生的工作量进行估算,等待变更委员会审批
正确答案及解析
正确答案
解析
本题考查的是变更的流程,发生变更要按变更控制流程来进行。是最基本的知识,必须掌握。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案