题目详情

当 ( ) 时,要正式通过变更审批。

  • A.0.7版的项目管理计划调整
  • B.某活动在自由时差内的进度调整
  • C.某活动负责人要求进度提前
  • D.项目经理安排一次临时加班

正确答案及解析

正确答案
C
解析

变更审批前提是大事,一般指改变基线需要变更审批,0.7版的项目管理计划还处于草稿,没有形成基线,无需变更审批;自由时差内的进度调整不影响整个关键路径,没有更改进度基线,无需调整;临时加班不涉及基线更改,也不需变更审批;而进度提前,则属于进度基线改变,需要变更审批。

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案