以下关于大型复杂项目和多项目管理的叙述中,不正确的是( )。
- A.大型复杂项目必须建立以过程为基础的管理体系
- B.为了确保大型复杂项目的过程制度起到预期作用,必须在项目团队内部建立统一的体系,包括制定过程、计划过程、执行过程
- C.大型复杂项目的项目过程确定后,再制定项目计划
- D.大型IT项目大都是在需求不十分清晰的情况下开始的,所以项目自然分成需求定义和需求实现两个主要阶段
正确答案及解析
正确答案
解析

你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案