关于典型的大型、复杂信息系统项目,下列做法中, ( ) 是不正确的。
- A.项目团队构成复杂,不仅包括项目内部人员体系,也包括合作方人员体系
- B.项目规模较大,目标构成复杂,往往分解成目标相互关联的小项目
- C.项目沟通成本大幅度上升,项目经理应该直接管理各子项目内的沟通
- D.项目管理方法与小型项目相比发生了根本的改变
正确答案及解析
正确答案
解析
对于大型复杂信息系统项目,项目经理应间接管理各子项目内的沟通,这样可以节约成本。
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案